Construction Management Online MCQ Test – Paper-3

0%
1 votes, 5 avg
4
Created by Nepal Lok Sewa

This is a FREE  Online MCQ test. Beware of scammers who ask for money to attend this test.

  • Total number of questions: 50
  • Time allotted: 35 minutes
  • Passing Score: 60%
  • Certificate: Yes
  • Random questions: Yes
  • Do not refresh the page
  • All the best!

1 / 50

1. No agreement is between:

2 / 50

2. When the times of earliest finish and the latest finish are equal in an operation, the operation is called:

3 / 50

3. The final technical authority of a project is:

4 / 50

4. What are the key dates of a standard contracting procedure for a project?

5 / 50

5. The salient feature of functional organization is:

6 / 50

6. In PERT technique, completion of an activity is called:

7 / 50

7. Policy is:

8 / 50

8. In PERT, pessimistic time is:

9 / 50

9. The dual-role event is:

10 / 50

10. Which of the following is not a part of a contract agreement?

11 / 50

11. The duration of time which an activity can be delayed without affecting the succeeding activity is called free float which affects only:

12 / 50

12. Insurance provision in GCC is applicable for:

13 / 50

13. At an event other than the final event, if no activity emerges, it results in an error called:

14 / 50

14. In resource leveling, the main constraint would be:

15 / 50

15. If the path of activities leads back into itself, the resulting error in the network is known as:

16 / 50

16. Henry Gantt developed the bar chart technique in:

17 / 50

17. If a is the optimistic time, b is the pessimistic time, and m is the most likely time, then the average time is equal to:

18 / 50

18. Aggregate planning is planning for:

19 / 50

19. The reduction in project time normally results in:

20 / 50

20. Milestone charts are developed in:

21 / 50

21. The maximum amount for the approval of tender by Gazetted 3rd class officer is:

22 / 50

22. The maximum amount of project cost after the price adjustment should not exceed:

23 / 50

23. A fictitious activity with zero duration and no cost used to maintain the sequential order of the activities in the network is known as a:

24 / 50

24. An EPC contract means:

25 / 50

25. PERT is:

26 / 50

26. A construction schedule is prepared after collecting:

27 / 50

27. The constraint in the case of resource smoothing operation would be:

28 / 50

28. An example of a parallel activity is:

29 / 50

29. According to Fulkerson's, the correct event numbers corresponding to events A, B, C, D, E of the network shown in figure 1 are:

30 / 50

30. If σ1, σ2, σ3..... are the standard deviations of completion for the activities along the critical path, the standard deviation of the time of completion of the project is given by:

31 / 50

31. The difference between total float and free float is called interfering float which is nothing but the:

32 / 50

32. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called:

33 / 50

33. Choose the most correct statement from the following:

34 / 50

34. The square root of the variance is known as:

35 / 50

35. For a ╬▓-distribution curve, if to is the optimistic time, tp is the pessimistic time, and tm is the most likely time, then the standard deviation will be equal to:

36 / 50

36. Who is responsible for accidents occurring at the site?

37 / 50

37. Crash project duration is obtained by adding the:

38 / 50

38. Muster rolls are used for:

39 / 50

39. 'Wait' in CPM belongs to the category of:

40 / 50

40. SLACK time refers to:

41 / 50

41. The main disadvantage of line organization is:

42 / 50

42. The variance will be zero if:

43 / 50

43. Which type of tender generally prefers the schedule of rate?

44 / 50

44. Residential buildings are treated as:

45 / 50

45. The minimum number of consulting firms for the direct purchase of services is:

46 / 50

46. The expected project duration in CPM follows:

47 / 50

47. Military organization is known as:

48 / 50

48. Total project time is the:

49 / 50

49. A golden rule for the procurement of construction work suggests:

50 / 50

50. The Force Account or AMANAT, a method of carrying out the construction work is done by:

Please provide accurate information to ensure the delivery of your Achievement Certificate by mail.

Your score is

Share your achievement.

LinkedIn Facebook Twitter
0%

Please write your feedback

Thanks for giving your valuable feedback.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top