Construction Management Online MCQ Test – Paper-3

0%
0 votes, 0 avg
2
Created by Nepal Lok Sewa

This is a FREE  Online MCQ test. Beware of scammers who ask for money to attend this test.

  • Total number of questions: 50
  • Time allotted: 35 minutes
  • Passing Score: 60%
  • Certificate: Yes
  • Random questions: Yes
  • Do not refresh the page
  • All the best!

1 / 50

1. The slack for an event is given by:

2 / 50

2. In CPM, the actual performance of a task is called:

3 / 50

3. Bar chart is used for minor projects, CPM is used for repetitive work while PERT is used for:

4 / 50

4. Which of the following is an event in a CPM network:

5 / 50

5. Bar chart is drawn for:

6 / 50

6. Slack time in PERT analysis:

7 / 50

7. PERT technique of network analysis is useful for:

8 / 50

8. Gantt chart is used for:

9 / 50

9. Who is responsible for accidents occurring at the site?

10 / 50

10. Choose the most correct statement from the following:

11 / 50

11. Free float for any activity is defined as the difference between:

12 / 50

12. No agreement is between:

13 / 50

13. Crashing of the project means:

14 / 50

14. Residential buildings are treated as:

15 / 50

15. Total float for any activity is defined as the difference between:

16 / 50

16. In CPM:

17 / 50

17. The term CPM in construction management is an abbreviation of:

18 / 50

18. Earliest finish time of an activity is always:

19 / 50

19. Force majeure in a contract is:

20 / 50

20. Find the variance if tp = 14 days, tm = 6 days, and to = 2 days:

21 / 50

21. Bar charts are considered suitable for:

22 / 50

22. The pictorial representation of activities and events of a project is known as:

23 / 50

23. The amount of money paid to the contractor by the client after the agreement and before the execution of work is known as:

24 / 50

24. The interrelationship between the functional elements of a program is achieved through:

25 / 50

25. Direct cost of a project is due to:

26 / 50

26. Performance security is necessary:

27 / 50

27. Time and progress chart of construction is known as:

28 / 50

28. CPM family includes:

29 / 50

29. Updating may result in:

30 / 50

30. Gantt chart is drawn for:

31 / 50

31. Positive float can occur when it is:

32 / 50

32. The district rate finalizing committee does not include the representative of:

33 / 50

33. For completion of a project, the critical path of the network represents:

34 / 50

34. In resource leveling, the main constraint would be:

35 / 50

35. The main disadvantage of line organization is:

36 / 50

36. The square root of the variance is known as:

37 / 50

37. CPM network is:

38 / 50

38. The time by which the particular activity can be delayed without affecting the preceding and succeeding activities is known as:

39 / 50

39. Line & staff organization is mostly suitable for:

40 / 50

40. The minimum number of consulting firms for the direct purchase of services is:

41 / 50

41. What are the key dates of a standard contracting procedure for a project?

42 / 50

42. The total cost versus time curve of an activity is:

43 / 50

43. Which type of tender generally prefers the schedule of rate?

44 / 50

44. The overall in-charge of an organization at the site responsible for the execution of works is:

45 / 50

45. Critical path is:

46 / 50

46. The technique for establishing and maintaining priorities among various jobs of a project is known as:

47 / 50

47. If a is the optimistic time, b is the pessimistic time, and m is the most likely time, then the average time is equal to:

48 / 50

48. Free float is the:

49 / 50

49. Policy is:

50 / 50

50. SLACK time refers to:

Please provide accurate information to ensure the delivery of your Achievement Certificate by mail.

Your score is

Share your achievement.

LinkedIn Facebook Twitter
0%

Please write your feedback

Thanks for giving your valuable feedback.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top