Construction Management Online MCQ Test – Paper-2

0%
0 votes, 0 avg
3
Created by Nepal Lok Sewa

This is a FREE  Online MCQ test. Beware of scammers who ask for money to attend this test.

  • Total number of questions: 30
  • Time allotted: 30 minutes
  • Passing Score: 40%
  • Certificate: No
  • Random questions: Yes
  • Do not refresh the page
  • All the best!

1 / 30

1. When all the paths are arranged according to the descending order of the float, the path which is next to the critical path is known as:

2 / 30

2. What are the key dates of a standard contracting procedure for a project?

3 / 30

3. Bar chart is used for minor projects, CPM is used for repetitive work while PERT is used for:

4 / 30

4. In PERT, pessimistic time is:

5 / 30

5. Aggregate planning is planning for:

6 / 30

6. The independent float affects only:

7 / 30

7. The slack for an event is given by:

8 / 30

8. Construction team means:

9 / 30

9. Which method is known as the minimum cost or maximum time schedule method:

10 / 30

10. Direct cost of a project is due to:

11 / 30

11. The reduction in project time normally results in:

12 / 30

12. Restraint is a restriction having:

13 / 30

13. PERT is:

14 / 30

14. The difference between the total float and the free float is termed as:

15 / 30

15. Residential buildings are treated as:

16 / 30

16. Which of the following time estimates is related to PERT?

17 / 30

17. In PERT analysis, the actual performance of the task is known as:

18 / 30

18. Positive float can occur when it is:

19 / 30

19. The mean of squared deviation from the mean of the distribution is known as:

20 / 30

20. Critical path network helps the engineer to:

21 / 30

21. Completion of an activity on the CPM network diagram is generally known as:

22 / 30

22. Total float for any activity is defined as the difference between:

23 / 30

23. If σ1, σ2, σ3..... are the standard deviations of completion for the activities along the critical path, the standard deviation of the time of completion of the project is given by:

24 / 30

24. The figure indicates:

25 / 30

25. Probability factor in PERT is given by:

26 / 30

26. The variance will be zero if:

27 / 30

27. If D is the duration, ES and EF are the earliest start and earliest finish time, LS and LF are the latest start and latest finish time, then the following relation holds good:

28 / 30

28. In PERT analysis, the time estimates of activities and the probability of their occurrence follow:

29 / 30

29. The occurrence of the completion of an activity is called its:

30 / 30

30. The meaning of modular coordination in construction is:

Your score is

Share your achievement.

LinkedIn Facebook Twitter
0%

Please write your feedback

Thanks for giving your valuable feedback.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top