HomeEngineeringCivil Sub Engineering Online MCQ TestConstruction Management Online MCQ Test – Paper-2Construction Management Online MCQ Test – Paper-20% 0 votes, 0 avg 3 Sorry, Time out. To complete the Quiz please Restart again. Created by Nepal Lok SewaThis is a FREEÂ Online MCQ test. Beware of scammers who ask for money to attend this test.Total number of questions: 30Time allotted: 30 minutesPassing Score: 40%Certificate: NoRandom questions: YesDo not refresh the pageAll the best! 1 / 301. The occurrence of the completion of an activity is called its: A) Head event B) Tail event C) Dual-role event D) All of the above 2 / 302. The completion report includes: A) The details of the final bill paid to the contractor B) The details of all the bills paid to the contractor C) The details of all the bills, variations along with as-built drawings D) The compilation of all the documents during project implementation 3 / 303. The figure indicates: A) An event B) Activity C) Burst D) Merge 4 / 304. PERT technique of network analysis is useful for: A) Small projects B) Large projects C) Research and development projects D) All of the above 5 / 305. Who is responsible for accidents occurring at the site? A) Petty contractor B) Himself C) Consultant D) Contractor 6 / 306. A dummy activity in CPM: A) Has no tail event but has only a head event B) Has only a head event but no tail event C) Does not require any resources or any time D) Has no sequence and can be fitted anywhere 7 / 307. The objective of technical planning is: A) Preparation of specifications and estimates B) Initiating the procurement action of resources C) Taking remedial action about bottleneck in execution D) All of the above 8 / 308. tij and tijE indicate the time required for the completion of an activity in CPM and PERT, respectively. Here the subscript E stands for: A) Uncertainty factor concerned with PERT B) Certainty factor concerned with PERT C) Certainty factor concerned with CPM D) All of the above 9 / 309. The area under the B-curve is divided into two equal parts by: A) Expected time B) Optimistic time C) Pessimistic time D) Most likely time 10 / 3010. Direct cost of a project is due to: A) Establishment charges such as salaries to administrative staff B) Loss or gain of revenue C) Penalty imposed D) Cost of materials and wages of labor 11 / 3011. Of the following, the PERT event is: A) Fixing of doors B) Plastering of walls C) Concrete cured D) Selection of sites 12 / 3012. An example of a parallel activity is: A) Completing ground floor and starting first floor construction B) Wall construction and carpentry work of doors and windows C) Completion of flooring and initiating whitewashing D) Digging of a well and construction of a septic tank 13 / 3013. Which type of tender generally prefers the schedule of rate? A) Schedule of rate B) Cost change C) Basic charge D) None of the above 14 / 3014. Critical path network helps the engineer to: A) Concentrate his attention on critical activities B) Divert the different resources from non-critical activities to critical activities C) Be cautious for avoiding any delay in the critical activities D) All of the above 15 / 3015. In CPM method, the earliest finish is indicated by time on: A) Top right, outside the circle, in a triangle B) Top right, outside the circle, in a rectangle C) Both of the above D) None of the above 16 / 3016. The salient feature of functional organization is: A) Strict adherence to specifications B) Separation of planning and deficiency C) Each individual maintains a functional design part D) All of the above 17 / 3017. In time cost optimization using CPM, the crashing of activities along the critical path is done starting with the activity having: A) Highest cost slope B) Least cost slope C) Crashing has no relation with cost slope D) None of the above 18 / 3018. The square root of the variance is known as: A) Deviation B) Standard deviation C) Mode D) None of the above 19 / 3019. The cost corresponding to crash time is: A) Direct cost is maximum B) Indirect cost is minimum C) Total cost may be maximum D) All of the above 20 / 3020. Probability factor in PERT is given by: A) (Scheduled time - Earliest expected time) / Standard deviation B) (Scheduled time - Latest allowable time) / Standard deviation C) (Latest allowable time - Scheduled time) / Standard deviation D) (Latest allowable time - Earliest expected time) / Variance 21 / 3021. A frequency distribution curve: A) Having a single lump is called a uninodal curve B) If symmetrical is called a normal curve C) If unsymmetrical is called a skew curve D) All of the above 22 / 3022. Free float is the: A) Portion of independent float B) Portion of positive total float C) Portion of interfering float D) All of the above 23 / 3023. The technique for establishing and maintaining priorities among various jobs of a project is known as: A) Event flow scheduling technique B) Critical ratio scheduling C) Slotting technique for scheduling D) Short interval scheduling 24 / 3024. The maximum amount for the approval of tender by Gazetted 3rd class officer is: A) Three crore B) Seven crore C) Fifteen crore D) More than fifteen crore 25 / 3025. Time and progress chart of construction is known as: A) Bar chart B) Gantt chart C) CPM D) All of the above 26 / 3026. Line of balance technique is used for: A) Planning of a project B) Planning of an activity C) Planning of an event D) Comparison of actual progress with the scheduled progress 27 / 3027. Tender documents do not contain: A) Tender form B) BOQ C) Amount of earnest money D) Unit rate 28 / 3028. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is: A) 3 days B) 4 days C) 5 days D) 6 days 29 / 3029. Negative slack occurs: A) When a deficiency of resources exists B) When the latest allowable time is greater than the earliest expected time C) When events stick to their schedule D) None of the above 30 / 3030. The latest allowable time for any event i is equal to: A) Minimum of (T<sub>L</sub><sup>j</sup> - T<sub>E</sub><sup>ij</sup>) B) Maximum (T<sub>L</sub><sup>j</sup> - T<sub>E</sub><sup>ij</sup>) C) T<sup>j</sup>L - T<sup>ij</sup>E D) None of the above Your score isShare your achievement. LinkedIn Facebook Twitter 0% Restart Test Please write your feedbackThanks for giving your valuable feedback. Send feedback