Construction Management Online MCQ Test – Paper-2

0%
0 votes, 0 avg
3
Created by Nepal Lok Sewa

This is a FREE  Online MCQ test. Beware of scammers who ask for money to attend this test.

  • Total number of questions: 30
  • Time allotted: 30 minutes
  • Passing Score: 40%
  • Certificate: No
  • Random questions: Yes
  • Do not refresh the page
  • All the best!

1 / 30

1. Which of the following time estimates is related to PERT?

2 / 30

2. When the times of earliest finish and the latest finish are equal in an operation, the operation is called:

3 / 30

3. The time below which the duration cannot be further reduced is known as:

4 / 30

4. SLACK time refers to:

5 / 30

5. The expected project duration in CPM follows:

6 / 30

6. Total project time is the:

7 / 30

7. Economic saving of time is obtained by crashing:

8 / 30

8. What are the key dates of a standard contracting procedure for a project?

9 / 30

9. Float is:

10 / 30

10. Time and progress chart of construction is known as:

11 / 30

11. If the completion time for a particular project is 6 weeks and its expected time is 8 weeks, then the slack time for the project is:

12 / 30

12. In a CPM/PERT network, the number of events is:

13 / 30

13. Critical path network helps the engineer to:

14 / 30

14. In time cost optimization using CPM, the crashing of activities along the critical path is done starting with the activity having:

15 / 30

15. tij and tijE indicate the time required for the completion of an activity in CPM and PERT, respectively. Here the subscript E stands for:

16 / 30

16. If an activity has its optimistic, most likely, and pessimistic times as 2, 4, and 6, respectively, then its expected time and variance are respectively:

17 / 30

17. The activity which neither takes time nor cost for its completion but is logically required to start the succeeding activity is known as:

18 / 30

18. An event is:

19 / 30

19. Direct cost of a project is due to:

20 / 30

20. Construction team means:

21 / 30

21. At an event other than the final event, if no activity emerges, it results in an error called:

22 / 30

22. PERT is:

23 / 30

23. Completion of an activity on the CPM network diagram is generally known as:

24 / 30

24. Find the variance if tp = 14 days, tm = 6 days, and to = 2 days:

25 / 30

25. The variance will be zero if:

26 / 30

26. If a is the optimistic time, b is the pessimistic time, and m is the most likely time, then the average time is equal to:

27 / 30

27. Free float is mainly used to:

28 / 30

28. The figure indicates:

29 / 30

29. Crashing of the project means:

30 / 30

30. Type of organization used in the construction industry is:

Your score is

Share your achievement.

LinkedIn Facebook Twitter
0%

Please write your feedback

Thanks for giving your valuable feedback.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top